Document from CIS Legislation database © 2003-2025 SojuzPravoInform LLC

RESOLUTION OF THE PRESIDENT OF THE REPUBLIC OF UZBEKISTAN

of July 24, 2021 No. PP-5193

About measures for the organization of construction of steam-gas power plant capacity of 1500-1600 MW in the Surkhandarya region

(as amended of the Resolution of the President of the Republic of Uzbekistan of 05.07.2023 No. PP-215)

For the purpose of stable providing the population and industries of economy with energy resources:

1. Take into consideration that:

a) between the Ministry of investments and foreign trade, the Ministry of Finance, the Ministry of Economic Development and reducings poverty, the Department of Energy, Agency on development of public-private partnership and the Stone City Energy company (Netherlands) (further - the Investor) on September 26, 2020 signed the document reflecting the main terms of agreement on implementation of the investment project on construction of steam-gas power plant capacity of 1500-1600 MW in the Surkhandarya region cost 1, of 2 billion US dollars (further - the Investment project) at the expense of direct foreign investments;

b) for the purpose of implementation of the Investment project by the Investor SCE Quvvat LLC is created (further - the Project company);

c) between the Government of the Republic of Uzbekistan on behalf of the Ministry of investments and foreign trade, the Investor and the Project company the Investment agreement (further - the Investment agreement) on April 22, 2021 is signed according to which the Investor and the Project company perform:

designing, financing, construction and operation within 25 years of steam-gas power plant capacity of 1500-1600 MW in the Surkhandarya region;

attraction of direct foreign investments in the amount of 1, 2 billion US dollars with acceptance on possible risks;

d) within the Investment project between JSC Natsionalnye elektricheskiye seti Uzbekistana and the Project company the Purchase agreement of the electric power (further - the Purchase agreement of the electric power) on April 22, 2021 is signed according to which:

The project company as ensuring execution of the obligations up to standard in the period of construction provides the bank guarantee in the amount of 30 million US dollars;

The project company assumed obligation of the guaranteed sale of the made electrical energy to the single buyer on behalf of JSC Natsionalnye elektricheskiye seti Uzbekistana;

Document in demo-mode!

Full text is available after subscription.

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.