of February 7, 2023 No. 18
About introduction of amendments to the order of the Minister of national economy of the Republic of Kazakhstan of December 5, 2014 No. 129 "About approval of Rules of development or adjustment, conducting necessary examinations of the investment offer of the state investment project, and also planning, consideration, selection, monitoring and assessment of realization of budget investments and determinations of feasibility of budget crediting"
I ORDER:
1. In the order of the Minister of national economy of the Republic of Kazakhstan of December 5, 2014 No. 129 "About approval of Rules of development or adjustment, conducting necessary examinations of the investment offer of the state investment project, and also planning, consideration, selection, monitoring and assessment of realization of budget investments and determinations of feasibility of budget crediting" (it is registered in the Register of state registration of regulatory legal acts for No. 9938) the following changes:
in Rules of development or adjustment, conducting necessary examinations of the investment offer of the state investment project, and also planning, consideration, selection, monitoring and assessment of realization of budget investments and the determinations of feasibility of budget crediting approved by the specified order:
54) of Item 2 to state the subitem in the following edition:
"54) pilot project – the investment project planned to realization within the order of the President of the Republic of Kazakhstan on construction of facilities in spheres of health care, education, housing construction in the city of Astana, Jambyl and North Kazakhstan areas provided in documents of System of state planning;";
to state paragraph two of Item 14 in the following edition:
"The documents specified in subitems 1) and 2) of Item 6 of these rules are signed by the first head of state body – ABP either replacement his face, or the face authorized by the first head of state body – ABP.";
state Items 15 and 16 in the following edition:
"15. ABP create and represent to the central or local authorized body on state planning the investment offers of GIP including the documents specified in Item 6 of these rules.
For single system of electronic document management documents make sure by means of the electronic and digital signature.
In case of lack of single system of electronic document management the investment offer is introduced on paper. The investment offer are polistno initialed or stitched, numbered and are certified by the signature of the head of the structural unit of ABP responsible for development of the investment offer.
16. In case of absence according to Item 6 of these rules of complete document package availability of which is necessary for preparation of the economic conclusion, the central or local authorized body on state planning returns the investment offer of GIP ABP.";
state Item 127 in the following edition:
"127. Chapter "Strategic premises" contains information on strategic documents in which implementation Investments are planned (the annual President's letter of the Republic of Kazakhstan to the people of Kazakhstan about provision in the country and the main directions of domestic and foreign policy of the Republic of Kazakhstan, regulatory legal acts, documents of System of state planning of the Republic of Kazakhstan, the budget program, orders of the President of the Republic of Kazakhstan).";
to state paragraph two of part two of Item 136-3 in the following edition:
"surname, name, middle name of person (in the presence) (name of the organization);";
the paragraph one of Item 148 to state in the following edition:
"148. In case of the direction of unused balances on control accounts of cash, current accounts in the form of economy of the budgetary funds which developed following the results of realization of one and more FEO of one subject of the quasi-public sector on implementation of the new project(s) development of new FEO of Investments according to the procedure, established by the budget legislation of the Republic of Kazakhstan is required.";
state Item 182-38 in the following edition:
"182-38. In the institutional Section the offered effective scheme of project management, their function, procedure for their interaction is described, at the same time the scheme is described to the level of the main participants signing the credit agreement.
This Section includes:
1) information on each participant of the financial scheme, and also the financial scheme of implementation of actions with indication of the amounts and the directions of cash flows;
2) information on strategic premises of the project in which realization actions for FEO of budget credit are planned (the annual President's letter of the Republic of Kazakhstan to the people of Kazakhstan about provision in the country and the main directions of domestic and foreign policy of the Republic of Kazakhstan, regulatory legal acts, documents of System of state planning of the Republic of Kazakhstan).";
state Item 182-46 in the following edition:
"182-46. Economic examination of FEO of the budget credit including corrected of the legal entity determined by the Government of the Republic of Kazakhstan or local executive bodies is carried out within 26 (twenty six) working days from the date of representation of document package on financial and economic reasons for the budget credit including corrected.
Economic expertize of FEO of budget credit is carried out based on the provided FEO of budget credit, the positive industry conclusions of authorized bodies, the positive decision of executive body of the specialized organization and the corresponding positive conclusions of the examinations required depending on specifics of the project.
Economic expertize is carried out only on the required amount of budget crediting of the specialized organization for the project based on FEO, the positive industry conclusions of authorized bodies, the positive decision of executive body of the specialized organization.
In case of need provisions of the additional information and (or) conducting additional examinations on the questions which are not covered or not completely covered by the carried-out expertizes and/or independent examination and also in the provided documentation, the corresponding legal entities determined by the Government of the Republic of Kazakhstan or local executive bodies on implementation of economic examination of FEO of the budget credit including corrected request the relevant information and (or) conducting additional examinations.
The financial reporting of participants constituted the last day of the month preceding introduction of FEO of the budget credit including corrected in the central or local authorized body on state planning and also explanatory notes to the financial reporting belongs to the additional information.
Treat additional examinations:
1) complex non-departmental examination;
2) industry examination of authorized state body.
Requests on submission of necessary information and (or) conducting additional examinations on the questions which are not covered or not completely covered by the carried-out expertizes go to the corresponding administrator of the budget program, the copy of request – to the central or local authorized body on state planning within 10 (ten) working days from the date of receipt of complete document package specified in 182-36 these rules.
ABP provide necessary information to the legal entity determined by the Government of the Republic of Kazakhstan or local executive bodies on implementation of economic examination of FEO of the budget credit including corrected within 30 (thirty) working days from the moment of receipt of request in the form of the official letter.
In case of prolongation of term of conducting economic examination the legal entity determined by the Government of the Republic of Kazakhstan or local executive bodies on implementation of economic examination of FEO of the budget credit including corrected notifies the central or local authorized body on state planning on prolongation of conducting economic examination with appendix of the letter of ABP.
From the date of sending an inquiry and before submission of necessary information terms of conducting economic examination stop.
Result of economic examination of FEO of the budget credit including corrected is the positive conclusion or the negative conclusion, or the conclusion on completion.";
the paragraph one of Item 182-55 to state in the following edition:
"182-55. Determination of feasibility of budget crediting for the solution of tasks of social policy of the state is performed by the approval of the relevant document of System of state planning or modification and amendments in this document of System of state planning providing the actions planned to financing by means of budget crediting based on the following documents provided by local executive bodies:";
state Item 182-56 in the following edition:
"182-56. The draft document of System of state planning, and also in case of modification and amendments of this document of System of state planning providing the actions planned to financing by means of budget crediting is subject to removal at the budget commission.";
the paragraph one of Item 191 to state in the following edition:
"191. Necessary information is prepared by administrators of republican budget programs and administrators of local budget programs quarterly to 10 (tenth) following reporting quarter in the Kazakh and Russian languages on paper and electronic carriers and contains:";
state Item 193 in the following edition:
"193. Annual monitoring on local the PIP, implemented at the expense of target transfers on development and the credits from the republican budget is represented administrators of local budget programs in the Kazakh and Russian languages in the relevant central state body, annually no later than March 10 of the year following for reporting.";
the paragraph one of Item 194 to state in the following edition:
"194. Annual monitoring on republican the PIP and local the PIP, implemented at the expense of target transfers on development and the credits from the republican budget is represented administrators of republican budget programs in the Kazakh and Russian languages in the central authorized body on state planning, including on the electronic portal annually no later than April 10 of the year following for reporting.";
the paragraph one of Item 195 to state in the following edition:
Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info
Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system
If you cannot find the required document, or you do not know where to begin, go to Help section.
In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.
You also may open the section Frequently asked questions. This section provides answers to questions set by users.