It is registered
in the Ministry of Justice
Kyrgyz Respubiliki
On August 10, 2007 No. 79-07
of July 23, 2007 No. 69
About approval of the Regulations on costs planning for forming of rate, accounting and calculation of cost of services in transfer of electrical energy
For the purpose of improvement of determination of the principles, rules and procedures of planning, accounting and calculation of cost of services in transmission of electricity, essential simplification of interaction between production, transfer and electric power consumption of JSC NES Kyrgyzstana.
According to item 6 of the Regulations on the Ministry of Industry, Energy and Fuel Resources of the Kyrgyz Republic, the approved order of the Government of the Kyrgyz Republic of March 26, 2007 I order to No. 86:
1. Approve the Provision "About Costs Planning for Forming of Rate, Accounting and Calculation of Cost of Services in Transfer of Electrical Energy".
2. Direct this Provision "About Costs Planning for Forming of Rate of Accounting and Calculation of Cost of Services in Transfer of Electrical Energy" to state registration in the Ministry of Justice of the Kyrgyz Republic.
3. This Provision becomes effective after state registration in the Ministry of Justice of the Kyrgyz Republic and the subsequent official publication in the Tabloid of "Erkin-limited liability partnership", "Regulations of the Government of the Kyrgyz Republic, the ministries, State Committees, administrative departments, Social fund of the Kyrgyz Republic, National Bank of the Kyrgyz Republic and local self-government of the city of Bishkek".
4. Notify the Ministry of Justice of the Kyrgyz Republic on source of official publication of this order.
5. To impose control of execution of this order on Prospective development department of the industry and power and legal department of the ministry.
Minister I. Chudinov
It is registered
in the Ministry of Justice
Kyrgyz Respubiliki
On August 10, 2007 No. 79-07
Approved by the order of the Ministry of Industry, Energy and Fuel Resources of the Kyrgyz Republic of July 23, 2007 No. 69
1.1. General provisions
This Provision is constituted on the basis of requirements of International accounting standards and completely corresponds to Accounting policy of JSC Natsionalnaya Elektricheskaya Set Kyrgyzstana (further in the text of JSC NESK), to normative requirements of the current legislation for regulation of activities of power, accounting and the reporting in the Kyrgyz Republic.
The provision is developed for the purpose of forming of single approach in case of determination of structure of the costs included in the cost of services in transmission of electricity when pricing (rates).
JSC Natsionalnaya elektricheskaya set Kyrgyzstana including power networks and substations of 110-220-500 kV and other devices and the equipment provides transformation of electrical energy and transfer (transportation) to its potrebitelyamraspredelitelny power companies (REK), large industrial consumers (LIC), for export and to others.
The service fee on transfer of electrical energy on high-voltage networks of JSC NESK is applied to the following consumers of services:
1. REK;
2. CHECK POINT;
3. ES - to the developing sources (by agreement)
4. for export (adjacent power supply systems);
5. to other organizations and companies.
JSC Natsionalnaya elektricheskaya set Kyrgyzstana includes the following functions:
- use of production capacities of NESK connected with transfer of electrical energy on networks of 110-500 kV for subjects of energy market;
- supervisory control of national power grids (operator of power supply system);
- observance of the approved reliability parameters (time of emergency idle times, stays under repair);
- the management of the modes of production and consumption of electrical energy and capacity in the Kyrgyz power supply system in real time realizing conditions of agreements of purchase - sale, transfer and electric power consumption (the operator of power supply system);
- the management of the modes of interstate overflows of electrical energy and capacity in real time realizing conditions of agreements of purchase - sale, transfer and electric power consumption (the operator of power supply system);
- rendering services to subjects of adjacent power supply systems on regulation of frequency (covering of irregularity of daily schedules of overflows of capacity and transit of electrical energy on national power grids);
- provision of the measuring equipment or uchetnoizmeritelny dismissed for implementation with consumers of services;
- ensuring reliable and safe operation of the energy equipment in compliance with the existing standard rates and rules, implementation of repairs and testing, production of construction works, reconstruction and upgrades of the equipment;
- provision of information on development programs and handling capacity of power networks of NESK to subjects of energy market of electrical energy (capacity).
1.2. Purposes and tasks of provision
Main objective of this provision is determination of the principles, rules and procedures of planning, accounting and calculation of cost of services in transmission of electricity (other types of products, works and services) in JSC NESK having the main power lines and objects of electric grid economy carried to national power grid on the property rights or other legal causes.
The main task of this provision is forming of cost of services in transmission of electricity, for adequate redistribution of the made economic cost, for the benefit of development of energy potential of JSC NESK in production and financial accounting.
At the same time the Provision carries out the following complex of tasks:
- ensuring technical reasons for production costs of JSC NESK on safety, reliability and uninterruptedness of electric supply of consumers;
- reflection of actual economic cost in the course of transfer of electrical energy on stages of engineering procedure;
- reasons for the planned, considered and calculated costs for transmission of energy for determination of rate for electrical energy (other types of products, works and services);
- expression of the general principles and rules on planning, accounting and calculation of cost of electrical energy (other types of products, works and services).
2.1. Features of production process
The utility power system of the company of power networks consists of the equipment, relay protection, automatic equipment and telemechanics. All these devices and the equipment provide continuity of transmission of electricity from electric utility service sources to consumers, maintenance of tension, frequency, sinusoidal form of electric current in the regulated parameters.
The main consumer requirements to utility power system is ensuring reliability and safety of operation of devices, that is accomplishment of project functions and operational parameters by them in the set limits during the established periods.
Management of reliability and uninterruptedness of electric utility service consists in the prevention of refusals of different elements of power networks which can lead to violation of engineering procedures of consumers, and also bystry recovery of the broken electric utility service without causing essential damage to consumers of electrical energy.
Reliable operation of the equipment and devices of electric utility service is provided with the organization of system of repair and operational servicing which includes in supervision of operation of the equipment preventive testing, the current and capital repairs.
For all elements of power networks optimum terms of periodic surveys, prevention and repairs are established. These terms depend on the number of repair work, quality of the used materials and spare parts and are determined differentially for different devices depending on local service conditions and specifics of operating modes of consumers.
Regular electric utility service provides reducing to minimum of planned shutdowns of consumers. It imposes increased requirements to work of the companies of power networks for planning and the organization of scheduled maintenance on the prevention of refusals, holding actions for increase in reserve maintenance periods and reducing duration of the repairs requiring shutdown of power supply of consumers.
The prevention of refusals in power supply of consumers is provided with system of capital and running repairs of the equipment and devices, and also modernization of objects of power networks - upgrade or replacement of the equipment, enhancement of devices of relay protection and telemechanics, equipment of objects with devices of the precautionary alarm system and others. At the same time also preventive planned actions on prevention of seasonal flows of refusals and first of all maximum demands and specific modes of work in autumn and winter conditions are important.
In work of the companies of power networks the actions connected with control and the analysis of refusals of power supply are of great importance. These actions include:
- precautionary information on possible refusals which is determined by indicators of stationary and figurative devices or messages of personnel on duty. The warning information on the revealed defects shall be fixed in special magazines and requires development of measures for immediate elimination of the found shortcomings;
- operational analysis of precautionary information. It is carried out within year and provides investigation of cases of refusals, their systematization. identification of tendencies in deterioration in condition of specific elements of power networks and their liquidation.
- statistical (for row of years) the analysis of refusals of power supply. He allows to establish main types steady and unstable power networks of damage, to determine parameters of flow of refusals and optimum terms of their elimination.
It should be noted that the main features of energy production also are:
- lack of work in progress;
- impossibility of warehousing and accumulating of energy;
- irregularity of production and transfer of electrical energy, in connection with seasonal fluctuations of its consumption in year (quarter), in month (daily allowance) and in days (sentries) which predetermine the variable mode of its transfer in networks of high voltage.
2.2. Production process tasks
During operation of the equipment and devices of power supply there is their natural aging and depreciation. One of the main production objectives of the company of power networks is holding actions for increase in operability of power supply facilities. It is performed by accomplishment of system of capital and running repairs of the equipment and devices.
The system of repairs of devices of power supply is classified by number of signs. On content of the performed works repairs are subdivided into capital, running repair and between-repairs servicing. On carrying out time repairs can be not the main, unplanned, postemergency and recovery.
Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info
Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system
If you cannot find the required document, or you do not know where to begin, go to Help section.
In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.
You also may open the section Frequently asked questions. This section provides answers to questions set by users.