Document from EA Legislation database © 2025-2026 EA Legislation LLC

Approved by the order of the Minister of Emergency Situations of the Republic of Kazakhstan of February 26, 2009 No. 36

Requirements of the device and safe operation of stationary compressor installations, air ducts and gas pipelines

(as amended of the Order of the Minister of Emergency Situations of the Republic of Kazakhstan of 21.10.2009 No. 244)

Chapter 1. General provisions

1. These Requirements extend to stationary piston and rotational compressors installed capacity from 14 kW and above, and also to vessels of compressor installations (air collectors, gas collectors, maslovlagootdelitel and other reservoirs), the air ducts and gas pipelines using air and inert gases with pressure from 0,2 to 40 MPas (from 2 to 400 kgfs/cm 2).

Requirements do not extend to designing, installation and operation of centrifugal and axial compressor machines; the compressors using explosive, toxic, radioactive gases and gases of acetylene series.

2. Designing of delivery pipelines of compressor installations is made according to these Requirements, the industry scientific and technical documentation (STD), construction regulations and requirements (Construction Norms and Regulations).

3. In pipeline project are specified:

1) settlement service life;

2) settlement resource;

3) settlement number of start-up (for the pipelines working under pressure of more than 4 MPas (40 kgfs/cm 2);

4) the size of trial pressure in case of hydraulic testing of the pipeline, MPa (kgf/cm 2);

5) hold time of the pipeline under trial pressure in case of hydraulic testing, min.;

6) pressure size during the testing of the pipeline for density, MPa (kgf/cm 2);

7) hold time of the pipeline with test pressure upon density, hour;

8) the admissible size of pressure drop in the pipeline in case of its testing for density, % an hour.

4. Materials (pipes, branch pipes, bent elements (knee), compensators, flanges, caps, laying, armature, electrodes, welding wire, bolts, hairpins, nuts and so forth), the methods and amount of control of welded connections applied in case of production, installation and repair of pipelines of compressor installations are determined by the project organization and are specified in the project.

5. All changes in the project are approved with the organization which developed the project.

6. Connection of elements, armature and details of pipelines is made by welding.

Application of flange connections is allowed only for connection of pipelines to armature and the details of the equipment having flanges.

Threaded connections are allowed for connection of instrumentations (manometers, sleeves of thermometers and so forth).

7. The Troynikovy connections produced from pipes with longitudinal seam are allowed to be applied to the pipelines working under pressure of no more 1,2 of MPa (12 kgfs/cm 2); at the same time quality check of welded seams on all length is carried out by radiography or ultrasonic defectoscopy (BRIDLES).

8. Pipelines and the bearing metal designs have reliable protection against corrosion.

9. All elements of pipelines with temperature of outside surface of wall it is higher than 45 hail. With, located in places, available to service personnel, become covered by thermal isolation which temperature of outside surface is not higher 45 hail. Page.

10. Vvark of unions, drain and blow-off tubes and other details in welded seams, and also in pipelines is not allowed.

11. The design of curvilinear elements (bent, cast, stamped) the pipeline conforms to requirements of the specifications and technical documentation.

12. Thickness of wall of bent element (knee) on any its site is at least values established by calculation on durability and TU on production.

The measurement of thickness of walls is checked by the technique specified in the specifications and technical documentation product.

13. The maximum ovality of cross section of knee is calculated on formula:

Формула 1 к Треб. уст. и безоп. экспл. стационарных компр. установок от 26.02.09 №36

where D, D - the maximum and minimum outer diameter of Hmax Hmin in the measured knee section respectively.

This ovality does not exceed the values provided by the specifications and technical documentation on product.

The variation from round form of bent sites of pipes is determined for each gib by results of measurements or controlled by means of limiting templates.

The size of thinning of wall in the most stretched part of gib of pipe "B" is determined by formula:

where SF - the actual thickness of wall of pipe, mm;

Smin-the minimum thickness of wall of pipe in the curve site, mm;

SH-nominal thickness of wall of direct pipe, mm.

The size of thinning of wall is checked by measurement of thickness of wall after the cutting of gib made in selective procedure at the discretion of the company owner of the pipeline.

The distance from outside surface of element which the pipe joins prior to the beginning of bend of pipe is at least outer diameter of pipe, but at least 50 mm.

14. All welded connections of pipelines are located so that the possibility of their control was provided with the methods provided by pipeline project.

15. Welding end-to-end with complete foundering is applied to connection of pipes and shaped details.

Angular welded connections are allowed for welding to pipelines of unions, pipes, flat flanges. Angular connections are carried out with complete foundering.

16. In joint welded connections of elements with the different thickness of walls smooth transition from bigger to smaller section by the corresponding unilateral or bilateral machining of the end of element with thicker wall is provided.

Tilt angle of surfaces of transitions no more than 15 hail.

17. When welding pipes and other elements with longitudinal and spiral welded seams the last are displaced one concerning another. At the same time shift is at least triple thickness of wall of the welded pipes (elements), but at least 100 mm. This requirement does not extend to pipes and elements with outer diameter less than 100 mm.

18. For cross joint welded connections the distance between axes of the next welded seams in direct sections of the pipeline makes at least triple thickness of wall of the welded pipes (elements), but at least 100 mm. Distance from axis of welded seam prior to the beginning of knee curve at least 100 mm.

19. In case of installation of steeply curved, stamped and shtamposvarny knees the arrangement of cross welded connections at the beginning of curve and welding among themselves of steeply curved knees without direct site is allowed.

20. For angular welded connections of pipes and unions with elements of pipelines the distance from outside surface of element prior to the beginning of gib of pipe or axis of cross joint seam makes:

1) for pipes (unions) with outer diameter up to 100 mm - is at least outer diameter of pipe, but at least 50 mm;

2) for pipes (unions) with the outer diameter of 100 mm and more - at least 100 mm.

21. The distance from axis of cross welded connection of the pipeline to edge of support or suspension bracket is chosen, proceeding from possibility of carrying out survey and control.

22. In case of elevated laying of air ducts and gas pipelines (inert gases) joint laying with technological pipelines of different function is allowed, except as specified, when such laying contradicts other requirements of industrial safety.

23. Armature is established in the places convenient for servicing and repair. In necessary cases ladders and platforms are arranged.

24. The bearing pipeline constructions, its support and suspension bracket (except for springs) are expected vertical loading from the mass of the pipeline filled with water and covered with isolation and the efforts arising from thermal expansion of pipelines.

Support and suspension brackets of pipelines are calculated without the mass of water in case of hydraulic testing, but taking into account the mass of working environment. In this case the project provides use of devices for unloading of springs, support and suspension brackets in case of hydraulic testing.

25. Motionless support are calculated on the efforts transferred to them in case of the most adverse combination of loadings.

26. The draw-off unions supplied with shutoff valves for emptying of the pipeline are provided in the lower points of each section of the pipeline which is disconnected by locking devices.

For removal of air in the upper points of pipelines vozdushnik are established.

27. All sites of pipelines which are disconnected by locking bodies for possibility of their purge, are supplied in trailer points with the union with the gate, and with pressure over MPa 2,2 (22 kgfs/cm 2) the union and two consistently located gates: locking and regulating.

The device of drainages provides possibility of control of their work during pipeline purge.

28. The lower trailer points of pipelines and the lower points of their bends are supplied with the device for purge.

29. Each pipeline for providing safe service conditions is instrumented for measurement of pressure and temperature of working environment, the locking and regulating fittings, safety valves, means of the alarm system, protection and automation.

The quantity and placement of armature, gages, automation, the alarm system and protection are provided by the project organization taking into account ensuring safe servicing and repair.

30. Armature has accurate marking on the case in which it is specified:

1) name or trademark of manufacturer;

2) conditional pass;

3) conditional pressure and temperature of the circle;

4) direction of flow of the circle (shooter);

5) steel brand.

In case of production of armature on industry standards instead of conditional pressure it is allowed to specify working pressure.

31. Delivery pipelines (air ducts, gas pipelines) of stationary compressor installations are subdivided on:

paid document

Full text is available after Signup and Login

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.