ORDER OF THE MINISTRY OF FUEL AND ENERGY OF UKRAINE

of June 9, 2005 No. 255

About approval of the Instruction about investigation and accounting of technological violations on power generation facilities and in the integrated power system of Ukraine

(as amended on 18-12-2023)

 According to Articles 5, 9, 16 and 20 Laws of Ukraine "About the market of electrical energy", the Regulations on the Department of Energy of Ukraine approved by the resolution of the Cabinet of Ministers of Ukraine of June 17, 2020 No. 507 concerning preserving integrity and ensuring reliable and effective functioning of the integrated power system of Ukraine and for the purpose of determination of procedure for the organization concerning investigation of classification and accounting of technological violations in work of power plants, power and thermal networks and power supply systems of electric power industry of Ukraine

I ORDER:

1. Approve the Instruction about investigation and accounting of technological violations on power generation facilities and in the integrated power system of Ukraine (further - the Instruction) which is applied.

2. To the director of the department of power industry Ulitich Yu. I. submit this Instruction on state registration to the Ministry of Justice of Ukraine in accordance with the established procedure.

3. To self-supporting division "Scientific and engineering power service center" of Ukrselyenergoproyekt institute (Bilousov V. I.) enter the Instruction in the register and computer databank of the existing regulatory legal acts of Mintoplivoenergo of Ukraine.

4. To merging of the energy companies "Industry Reserve Investment Fund of Development of Power" (Haydurov G. P.) to provide the edition and receipt of necessary number of copies of this Instruction to the energy companies and the power companies.

5. Orders of the Department of Energy of Ukraine of 27.01.99 N30 "About Approval of the Instruction about Investigation and Accounting of Technological Violations on Power Generation Facilities and in the Integrated Power System of Ukraine" and the Ministry of Fuel and Energy of Ukraine of 29.12.2004 N832 "About approval and commissioning of the regulating document "Investigation and accounting of technological violations on power generation facilities and in the integrated power system of Ukraine. Instruction." to cancel.

6. To impose control of execution of this order on the deputy minister Titenko S. M.

 

Minister I. Plachkov

Approved by the Order of the Ministry of Fuel and Energy of Ukraine of June 9, 2005 No. 255

The instruction about investigation and accounting of technological violations on objects of power and in the integrated power system of Ukraine

I. Terms and determinations of concepts

In this Instruction terms are used in such value:

automated control system for wind power plant (further - VES ACS) - system which is set of technical means (primary sensors, communication devices, computer facilities and so forth) and the software, intended for control of condition and parameters of operating mode of the equipment of wind power plant (further - VES) and controls of this equipment in the automatic mode or with the participation of personnel;

administrative technicians of energopredpriyatiyadirektor, technical leads, chiefs of departments, workshops, services, laboratories and their deputies;

variation of parameters - any variation of parameters of the energy carrier from project or established by the regime card;

recovery - event which is that after defect elimination object recovers capability again to perform the necessary function;

heat supply source - the generalized concept of sources of heat energy to which belong heating plant, the station of heat supply, the steam and water heating boiler rooms;

the energy carrier - substance or the phenomenon which can be used for accomplishment of mechanical work or heating, or for management of chemical or physical processes;

mass shutdowns of power lines - shutdown of 10 and more power lines of 35 kV, three and more power lines of 110 kV within one electrical power company as a result of the spontaneous phenomena which led to shutdown of consumers;

disabled condition - condition of object in case of which value of all parameters characterizing capability to perform the set functions, do not meet the requirements of normative and technical and/or design (project) documentation;

normal operation - condition of the equipment which answers the production technology accepted in the project and transfer of electrical and heat energy to consumers, including start-up stops, maintenance and repairs;

heat supply break - the termination of circulation of the heat carrier for any reason in thermal network or in the presence of circulation when heat energy is not released to consumers;

wrong actions - activities or divergence which brought or did not prevent emergence of technological violation;

violation of shop accounting - refusal which does not answer any of the signs given in Section 5 of this Instruction;

operating state - condition of object in case of which value of all parameters characterizing capability to perform functions, meet the requirements of normative and technical and/or design (project) documentation;

destruction - transition of object, installation to limiting condition upon which its further operation or recovery are impossible or inexpedient;

the sanitary protection zone - distance between the power company and the next residential or other buildings which is created for the purpose of protection of the population against influence of harmful production factors (harmful emissions, thermal and electromagnetic radiation, radiation, noise and so forth). It is established at the rate of not exceeding of these factors out of limits of the established predelnodopustimy sizes;

the spontaneous phenomena - exceeding of the key extreme parameters of the environment (wind speed, level and speed of movement of water, earthquake force, speed and size of ice and so forth) whom power stations and their separate elements are expected;

the workshop (site) - part of the energy company with equipment complex which performs certain functions for ensuring its normal functioning.

Document in demo-mode!

Full text is available after subscription.

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.