ORDER OF THE MINISTER OF NATIONAL ECONOMY OF THE REPUBLIC OF KAZAKHSTAN

of June 28, 2016 No. 288

About modification of the order of the Minister of national economy of the Republic of Kazakhstan of April 1, 2015 No. 299 "About approval of Rules of conducting complex non-departmental examination of the feasibility statements and the design estimates intended for construction new, and also changes (reconstruction, expansions, modernization, upgrade and capital repairs) the existing buildings and constructions, their complexes, engineering and transport communications irrespective of financing sources"

I ORDER:

1. Bring in the order of the Minister of national economy of the Republic of Kazakhstan of April 1, 2015 No. 299 "About approval of Rules of conducting complex non-departmental examination of the feasibility statements and the design estimates intended for construction new, and also changes (reconstruction, expansions, modernization, upgrade and capital repairs) the existing buildings and constructions, their complexes, engineering and transport communications irrespective of financing sources" (registered in the Register of state registration of regulatory legal acts for No. 10722, published in information system of law of Ad_let on April 21, 2015) the following change:

Rules of conducting complex non-departmental examination of feasibility statements and the design estimates intended for construction new, and also the changes (reconstruction, expansions, modernization, upgrade and capital repairs) the existing buildings and constructions, their complexes, engineering and transport communications irrespective of financing sources approved by the specified order to state in edition according to appendix to this order.

2. To provide to committee on cases of construction and housing and communal services of the Ministry of national economy of the Republic of Kazakhstan in the procedure established by the legislation:

1) state registration of this order in the Ministry of Justice of the Republic of Kazakhstan;

2) the direction of the copy of this order in printing and electronic type on official publication in periodic printing editions and information system of law"? d_lt" within ten calendar days after its state registration in the Ministry of Justice of the Republic of Kazakhstan, and also in the Republican center of legal information within five working days from the date of receipt of the registered order for inclusion in reference control bank of regulatory legal acts of the Republic of Kazakhstan;

3) placement of this order on Internet resource of the Ministry of national economy of the Republic of Kazakhstan;

4) within ten working days after state registration of this order in the Ministry of Justice of the Republic of Kazakhstan submission to Legal department of the Ministry of national economy of the Republic of Kazakhstan of data on execution of the actions provided by subitems 1), 2) and 3) of this Item.

3. To impose control of execution of this order on the supervising vice-minister of national economy of the Republic of Kazakhstan.

4. This order becomes effective after ten calendar days after day of its first official publication.

Minister of national economy of the Republic of Kazakhstan

K. Bishimbayev

Appendix

to the Order of the Minister of national economy of the Republic of Kazakhstan of June 28, 2016 No. 288

Approved by the order of the Minister of national economy of the Republic of Kazakhstan of April 1, 2015 No. 299

Rules of conducting complex non-departmental examination of feasibility statements and the design estimates intended for construction new, and also changes (reconstruction, expansions, modernization, upgrade and capital repairs) the existing buildings and constructions, their complexes, engineering and transport communications irrespective of financing sources

1. General provisions

1. These rules of conducting complex non-departmental examination of feasibility statements (further - the feasibility study) and the design estimates (further - the design and estimate documentation), intended for construction new, and also changes (reconstruction, expansions, modernization, upgrade and capital repairs) the existing buildings and constructions, their complexes, engineering and transport communications irrespective of financing sources (further - Rules) are developed according to subitem 11-5) of article 20 of the Law of the Republic of Kazakhstan of July 16, 2001 "About architectural, town-planning and construction activities in the Republic of Kazakhstan" (further - the Law).

2. Rules are established:

procedure for carrying out by the principle of "one window" of complex non-departmental examination of projects (preproject or the design and estimate documentation) constructions new and changes (reconstruction, expansion, modernization, upgrade, capital repairs) of the existing buildings, constructions, their complexes, communications, and also engineering training of the territory, improvement and gardening.

procedure for development and approval of individual plans of step-by-step development and approval of the design and estimate documentation for construction of the separate objects requiring special regulation and (or) town-planning regulation.

3. During by the principle of "one window" of complex non-departmental examination of construction projects of objects necessary industry examinations according to construction projects new, and also changes (reconstruction, expansions, modernization, upgrade and capital repairs) the existing buildings and constructions, their complexes, engineering and transport communications are performed.

Rules are obligatory for all subjects of the architectural, town-planning and construction activities performed in the territory of the Republic of Kazakhstan.

4. Rules extend to conducting examinations of the projects provided by subitems 1) and 2) of Item 1 of article 64-3 of the Law.

5. According to construction projects, specified in item 4 of article 64-1 of the Law complex non-departmental examination is not obligatory and it is carried out only at the discretion of the customer.

6. The complex non-departmental expertize of projects which is carried out state or the accredited expert organizations according to their competences established by articles 64-4 and 64-5 of the Law is performed based on contracts with reference of costs for cost of the considered project.

7. The cost of conducting complex non-departmental examination of construction projects is determined according to Items 2 and 3 of article 64-2 of the Law.

free document

Full text available after Login.

Disclaimer! This text was translated by AI translator and is not a valid juridical document. No warranty. No claim. More info

Effectively work with search system

Database include more 50000 documents. You can find needed documents using search system. For effective work you can mix any on documents parameters: country, documents type, date range, teams or tags.
More about search system

Get help

If you cannot find the required document, or you do not know where to begin, go to Help section.

In this section, we’ve tried to describe in detail the features and capabilities of the system, as well as the most effective techniques for working with the database.

You also may open the section Frequently asked questions. This section provides answers to questions set by users.